PROCEDURE FOR OBTAINING A BUILDING PERMIT
IN SEVIER COUNTY

plan checklist

What work requires a building permit?
No building shall be erected, constructed, enlarged, altered, repaired, moved, improved, moved, converted, or demolished unless a permit for each project has been obtained from the Sevier County Building Department.

Failure to obtain the necessary permit prior to beginning work will result in an investigation fee being added to the cost of the permit fee. The investigation fee will be the same as the permit fee, and you will still be charged for the permit (Double Fee).

Requirement for ALL commercial and residential projects
(For requirements on farm structures, contact John L. Hicks)

1. Submit two sets of plans to the Sevier County Building Department for review at least two weeks prior to wanting to start the project.

2. There is a $200 deposit required for all commercial plans submitted for the plan review process. The remainder will be collected with the building permit fee.

3. If building within city limits, you must have approval from the local zoning board prior to submitting your building permit. This is shown to us by an authorized signature on the zoning part of our permit.

4. If you are building in county limits, you must have a signature sheet completed to turn in with your building permit. This sheet needs the signatures of authorized Utah Power & Light personnel, authorized Utah Division of Water Rights personnel, and Central Utah Health Department personnel. (The signatures of the building inspector and zoning administrator will be provided by our office if permitted.)
  • The Central Utah Health Department will require you to purchase a septic tank permit, or show proof that you can hook up to an existing sewer system.
  • The Utah Division of Water rights will show us proof that you have an approved source of water. (Such as a well or other).
5. The application plans, specifications, and other data filed by an applicant for a permit shall be reviewed by the building official. Such plans may be reviewed by other departments of this jurisdiction to verify compliance with any applicable laws under our jurisdiction. If it is determined that the work described in an application for a permit and the plans, specs, and other data filed therewith conform to the requirements of the Uniform Building Code and other laws and ordinances, and the fees have been paid, the building official shall issue a permit therefore to the applicant.

GENERAL INFORMATION

  • Septic tanks are issued through the Central Utah District Health Department in Richfield, 70 West Westview Drive. Telephone 896-5451.
  • Well permits are issued through the Utah Division of Water Rights in Richfield, 130 N. Main Street. Telephone 896-4429.
  • Property serial numbers can be obtained from the County Recorder Office, 250 N. Main Street, Richfield, Utah. Telephone 893-0411.
  • City zoning permits can be obtained at the city office.
  • County permits and signature sheets can be obtained from our office.